In August 2020, the Town received confirmation that its application for the the Investing in Canada Infrastructure grant program (ICIP) was successful and it will receive $13.5M in funding from the federal and provincial governments to expand the current Dale Fisher Arena.
After proposing a scope change of this project from a recreation facility to a twinned arena due to affordability, the Town is still approved under the Federal ICIP program and the Government of Alberta endorsement for a combined total of $13.5 million.
The project was officially green lit on Nov. 1, 2022, by Town Council and a shovel ceremony was hosting on Apr. 19, 2023 to kick construction on the twin arena. Construction is expected to take about a year and a half with the twin facility ready to open in fall 2024!
Expanded Facility Amenities
New additions to loow forward to in the expanded facility include
Twin Arena Floor Plan
See the full PDFs of the internal and external plans here